The Gators and leading construction company Charles Perry Partners, Inc. (CPPI) have teamed up once again to improve the game day experience for Gator football fans. This fall, a renovated West Concourse will debut, resulting in renovated restrooms, concessions, and finishes throughout. As with other construction projects with CPPI at the University of Florida, the renovations are being done in accordance with industry leading sustainability initiatives.

 Project Updates

CPPI completes demolition, begins vertical construction on West Concourse Renovation at Ben Hill Griffin Stadium

With the assistance of Albert, Charles Perry Partners, Inc. (CPPI) completed the initial demolition phase of the West Concourse renovation project at Ben Hill Griffin Stadium. Read More

CPPI Partners with UAA for West Concourse Renovation at Ben Hill Griffin Stadium

Charles Perry Partners, Inc. (CPPI) started demolition and renovations of the West Concourse at the University of Florida's Ben Hill Griffin Stadium on Dec. 5, 2011, to improve the game day experience for Florida Gator Football fans. Read More

 Project Plan

Construction began on the West Concourse of Ben Hill Griffin Stadium in early December to improve on the already historic venue that is The Swamp. UF is excited to partner with CPPI on another athletic project that will bring both practical and aesthetic benefits to fans attending Florida Gator football games.

While the full scale of the project is still in the works, below is a short timeline highlighting what has been done and some of the more notable elements to be completed over the next several months.

Completed to Date

  1. Demolition complete
  2. 90% of Overhead utility removal / relocation
  3. Lower level vomitory walls poured and stripped
  4. 90% of Paint removal
  5. 60% of Masonry at the upper level concessions
  6. Upper level vomitory walls complete
  7. 90% of lower level plumbing
  8. 75% of electrical underground rough-in

April 2012

  • Work at the lower level concourse / concessions / kitchen will continue. The concourse concrete will be installed.

May 2012

  • Structural steel framing will begin.  All four gate entries will begin to see brick installation and work will be done on new restrooms and concession areas.  Overall the concourse will start to look like a stadium again during the month of May

June 2012

  • Framework and beginning of finishes throughout the area will be installed. Graphics, lights and ceilings will also be installed.
  • The new restroom renovations and family restrooms will be nearly complete with new tile, ceilings, lights, trim and fixtures.

July 2012

  • The last month of the project will see all trades wrapping up and finishes completed.  Doors and hardware will be installed. Stainless steel countertops, final equipment installation and final graphics will be installed.

Please continue to visit this page for updated information, pictures, and stories from start to finish on the Ben Hill Griffin Stadium West Concourse renovation project.

Photos

Renderings

 Charles Perry Partners, Inc.

Charles Perry Partners, Inc. (CPPI) is one of Florida's leading general contractors, construction managers and design-builders. Since 1968, the firm has established a tradition of excellence by providing an impressive array of services for public and private sector clients. CPPI's services cover a wide range, including project planning and modeling, budget estimating and cost management, project scheduling and construction. The firm is a leader in sustainability and dedicated to the communities in which it serves. For more information, please visit CPPI's website, follow CPPI on Twitter, or call 800-591-CPPI.

  • University of Florida
  • NCAA
  • Sun Sports / Fox Sports Florida
  • IMG
  • Sirius XM
  • SEC on ESPN

Copyright © 1998 - 2012 University Athletic Assoc., Inc., Sun Sports & IMG College. All Rights Reserved.